|
An analysis of the Talo Dam project and its foreseeable consequences on rural production systems in Djenneri
By Françis Gallier (5)
(Reprinted from: The Djenné Heritage Information Number
13, July 2002
Translation by the Djenné Initiative, Inc.)
(CLICK HERE for French Version)
The Talo Dam construction project on the Bani, upriver from the Niger Delta, is quite contested. In its current phase, this project, -initiated in the early 1980s- (6), calls for the settlement of 20.316 hectares, 10.030 for rice production, with controlled submersion enabled by the Dam. The Dam would allow the water levels to rise to a height of 274.35 meters on the site of a lateral threshold. In its dry decennial condition (7),
the effect would be to raise the water level more than 6 meters in Talo and 2.84
in Douna (80 kilometers upriver from the Dam). At this height, the reservoir
would have a volume of 175 million of cubic meters and a surface of 29 million
m2. (Agrer 1997).
The adoption of this project ignited the discontentment of...the local populations,
especially those located downstream from the new arrangement, namely those populations
who will...have to suffer the consequences of the hydrological transformations.
The concerns are strongest beyond San and all the way to Mopti; the Djenne inhabitants,
in particular, managed to stir up public opinion (8). Thus, the Djenné inhabitants'
association in Bamako expressed its concerns in a letter addressed to the President
of the Republic of Mali, titled: "The Djenné arguments regarding the Talo
Dam", dated October 28, 1998.
The main concerns [as to the impact of the Dam] are linked to:
- Reduction in the water levels during the flood period and consequently the loss of floodplains;
- The belatedness of the flood;
- Reduction in quality of the waters and their sediment content;
- The social and economical repercussions, for which -in the end- the economical interest is seriously put to test.
Nevertheless, both the opponents and the supporters of the Dam seem to lack complete and reliable studies. In particular, as for the impacts on the downstream areas, one has to deplore a lack of coherent, consistent and accurate projections that would allow for more constructive discussions, as well as more critical ones, so that decisions can be made in full knowledge of the issue... There is a real lack of information that I tried to fill in, within the limits of the means I had at my disposal for my DEA internship. Two main objectives were devised:
- To situate the project in its context and, through a critical analysis of the existing documents, reach an arguable opinion about the quality of the project preparation.
- To attempt to predict, through the use of various existing information and by deploying a map projection of the foreseeable transformations of a flooded zone chosen as an example, the hydrological impacts of the Talo Dam and its repercussions on the [traditional] downstream production systems.
Context and critical analysis
The presentation of the geographical context, climactic but also conceptual, seems indispensable to the correct grasp of the problem. The impacts will be felt in the flood zones of the interior Niger Delta, more to the south. The riches, but also the vulnerabilities, of those deltaic regions have already been revealed. The variability and unpredictability of the rains and floods determine the abundance and allocation of the natural resources, and thus, the life conditions of the populations, who for the main part have remained rural and agrarian. This explains how much the farmers (rice growers), herders and fishermen depend on the good quality of the floods from the adjacent Niger and Bani rivers; they are particularly sensitive to, and worried by, this Dam which presents a threat to them.
Situation Map of the Talo Dam on the Bani for the irrigation of the plains

These concerns are legitimate in regard to the international sphere. In
fact, in an international context, the politics of dam building are more and
more criticized. Civil societies, scientists and experts question their economical
profitability and relevance by demonstrating the negative impacts they carry.
Their capacity to generate a sustainable development is, in the end, quite debatable.
And so, it seems indispensable for this Dam project to take all necessary precautions
and to insure that the negative impacts will not outweigh the expected advantages.
In the specific case of the Talo Dam, the reflection on its interests and its
dangers should integrate the complex problems of the delta system development;
the diversity of the areas; the variability of the resources and the difficulties
that result from the coexistence of rice-growers, herders and fishermen. Do the
preparatory studies address those issues?
The critical analysis of the preparatory documents (9) revealed very important
failings:
- The hydrological transformations caused by the Dam [were] not considered
significant and so the downstream impacts are judged as negligible. In this manner
therefore, the extent of the studies conducted is rather inadequate; the influences
of the project on the Niger Delta have been systematically ignored. The needed
effort to anticipate the hydrological transformations for the downstream zone
and their repercussions on the areas and production systems upon which the local
societies and economies depend has not been exerted --with no visible explanation.
- The failure to consult, expressed by the citizens, has been recognized by
the Mission of the National Direction for the Control of Pollutions and Nuisances.
(DNACPN 2001).
- The failure to consider certain negative impacts linked, on the other hand,
to an ever optimistic vision of the hoped-for results forces us to question the
conclusion...that this project would bring an economic and social success and begs
for a real cost/benefit analysis.
- The fact that only the financing of the first phase of the work has been
secured, and the risk that the rest of the settlement work (in a second phase)
may never be financed (or may be but only after considerable delays), clearly
threatens the success of the program. In effect, short of the second phase, the
investments would be made profitable by the newly settled areas of the first
phase, namely, 7,850 hectares in controlled submersion, of which only 4,750 are
allocated for rice (11).
- More generally, a sound analysis is lacking for this project: there is no
reference to the known dangers of dams, to the recent evolution of the climactic
context, to the concepts of "sustainable development," to experiences acquired
on the development of the Niger Delta, and to the drawbacks of hydro-agricultural
settlements....
Consequently, further studies based on the projection of hydrological transformations
appear quite necessary. They would correct the main gaps and foster a better
debate, a better decision-making process favoring an economical and social development
respectful of the environment. These additional studies would demand the collection
of new basic information (topographical, hydrological, and land-related).
Nevertheless, we have tried here to foresee what would be the hydrological transformations
and their consequences, within the limits of our means and competences.
Prediction of the hydrological transformations of the affected areas
By using hydrological data specific to the elaboration of the project (12) and
linking them to the knowledge we have of the Bani River hydrology (13), we were
able to predict the main hydrological transformations that the project will cause.
Here are the essential results:
- The hydrological losses caused by the Dam (more than 90 million cubic meters
per decade in September, as per Agrer 1997, will induce a decline proportionate
to the available volumes downstream.
- There will be a drop in the water levels downstream. As per the rating curve
* in Bénéni-Kégny, a reduction of 20 to 45 cm is predictable
in flood conditions, whether good or bad, (like those of 1994 and 1993, which
represent those situations in our work.)
- The phase of filling up of the retaining lake (during which the water level
reaches downstream only though a floodgate construction limited to 10m3/sec.)
will delay the flood arrival for 10 to 20 days.
- At the moment when the Dam fills up, the water flows over it, and the flood
arrival will be more brutal. A daily increase of 5 to 7 cm can be feared with
a peak of 10cm daily at the beginning of the arrival of the "new waters".
- The drop in water level, on the other hand, won't be delayed, and so the
duration of the submersion finds itself reduced to 10 to 20 days.
- The unavoidable deposit of solid matters (siltation) in the containment area
leads to the decline of fertilizing supplies downstream. The increase of erosion
phenomena could entrench the river bed, further reducing the maximal heights
reached by the floods. The overflow, so expected, so necessary, could be limited.
- Finally, the upholding of a low water mark included between 5 to 10 cm/sec.
can only concern the inferior bed. It remains to be seen what will remain of
this water flow, minus the evaporation and the infiltrations along a few hundred
kilometers.
Predicting Hydrological Transformation
By using a Geographical Information System (ArcView), we were able to draw a
cartographical simulation of the reduction of the flooded areas that would have
resulted from the construction of the Dam under the 1993, 1994, 1995 flood conditions
-which are deemed, respectively, bad, good or average floods. To those years
we have added a simulation for the 2000 season in order to gather recent and
precise recollections from the farmers. As a basis, we had a topographical survey
scaled at 1/5000 from a part of the Casier Bougoula obtained from the Mopti Rice
Office (ORM) (14). The equidistance of the level curves is 0.2 meter and allows
for a satisfactory precision. We added hydrological data from ORM and from the
National Hydraulics Directorship (DNH), from which we subtracted the foreseeable
losses and heights due to the Dam. We have thus obtained a series of flood maps
for different years, one with the natural situation and one expected with the
Talo Dam...
As an example, see the Simulation map of the 1995 flood, excerpted from the dissertation
enclosed. The map on the left shows the flood that must have occurred in this
part of the Casier Bougoula in 1995 as per the hydrological data collected by
ORM at the entrance of the Casier. A certain agricultural potential, according
to the height of each billow, is allotted to each space. The map on the right
shows the flood that should have occurred in the event the Dam was built, according
to the projection of the hydrological transformations. Below, the bar chart shows
the evolution of the areas thus concerned by the billows and the associated potentials.
Thus, ArcView allows us to estimate the losses that can be deplored in terms
of floodable areas and agricultural potential.
Here is the main information that can be obtained with this method regarding
the flooded areas at different depths:
- The decrease of the inundated areas from the flooding varies with the considered
spaces and years, but it is all the more important when floods are mediocre.
- There are thresholds under which a weak drop of the water level induces a very
strong drop in the inundated surfaces. Thus the evolution of the flooded areas
is not linear and proportional to the height of the water site.
- If the average drop of the flood level is 30 cm, the decrease of the inundated
areas may be 20 to 90% in regard to the current situation (depending on places
and years under consideration). For the rest, we retain an average loss of 22%,
which corresponds to the weakest results, and therefore, the most optimistic
ones. However, even when retaining this weak hypothesis, the areas thus lost
would be very important and may in no way be neglected. To give an idea: in an
area of 53,060 hectares under the influence of the Bani, more than 12,000 would
have been lost, and 10,000 of the 44,000 farmed hectares would have been lost
in just the Pondori Plain in the year 2000, (as per data collected with a GPS
system by Care Djenné.)
Year 1995
Simulation of the impacts of the Talo Dam on the flooding of the Bougoula Plain

Projection of the repercussions of those hydrological transformations in rural
production systems
Agrarian productions in the floodable zones that interest us here constitute
a very complex system. Indeed, the coexistence of cultivation, fishing and husbandry
activities on a mosaic-like space, following precise seasonal occurrences, depend
on diverse factors (like rains and floods), for which links of cause and effect
are not linear. One must then adopt a more systematic approach.
Even in natural conditions, the deltaic production systems are very dependent
on pluviometric conditions and flood intensity. As a result, the productive activities
of the inundable zones are always random, for they depend on variable, unpredictable
and natural elements. People attempt to adapt themselves... to such elements, to
accommodate the climactic and hydrological rhythms with the biological contingencies
of diverse productions. But despite their efforts, they remain largely dependent
upon the random character of such hazards.
Indeed, one can always look for the species best adapted to the terrain, use
past experiences, diversify activities, move to where resources are more available...but
with their present financial and technical means, the rural producers remain
powerless in regard to weak rains or a bad flood. In addition, and to further
complicate production activities --resources have to be shared, coexistence amongst
local people must be insured, which is subject to negotiation of their [indigenous
rights to lands and resources], along with a rigorous respect for seasons and
natural conditions.
In fact, not only the quality and quantity of the production are random and exposed
to numerous risks, but also the "social peace", which depends on the respect
for a complex land-owning system that must be adapted and renegotiated in real
time depending on the land-owning/land-sharing conditions offered by the different
areas.
Therefore, one should be aware of the hydrological transformations that building
the Talo Dam (16) would cause, -increasing the risks that threaten sustainability
and testing the already fragile land owning systems. Here is, briefly stated,
how the main natural risks would be increased by the Talo Dam:
- Drying up of cultures: the rice seedbeds must be leavened with the rains, but
when the rains diminish at the end of wintering, it is important that the floods
reach and inundate the young sprouts to allow for maturation. However, the delay
of the flood caused by the filling up of the containment forebodes that, in certain
circumstances, the sprouts shrivel up or dry up before the flood's arrival.
- If the inundation of the rice paddies doesn't occur in desired quantity and
time, the harvest is lost. And with the Talo Dam, the proportion of the paddies
that won't receive any water will increase.
- If the flood arrives too strongly (if the water raises more than 3 to 5 cm
per day), the rice stalks could be submerged and "drowned." (This term is locally
employed, as this is also called a "white flood"). This is also true for other
vegetal species. The primary production of certain areas could be affected by
the Dam since, according to our research of the hydrological documents, the flood
would occur more brutally with rises of 10 cm a day.
- If the inundation of the paddies doesn't last long enough (2 to 4 months according
to the different types of rice), the plants risk not reaching maturity and the
harvests will be affected, or sometimes completely lost. Now, the Talo Dam delays
the arrival of the flood but doesn't delay the drop in level. The flooding of
the different areas is unavoidably shorter and the risk will rise significantly
(the farmers talk of a premature withdrawal.)
During the low water season, the drying up of the ponds and of the secondary
channels -where the herds drink and where the survival of a piscicultural fauna
is necessary for the next good fishing season- is always feared. However, with
the Talo Dam, a decrease of the ground water levels is to be feared downstream
and so is an earlier drying up of the water sources. This hypothesis remains
to be verified. In the event that it would, it is clear that the pastoral and
halieutic activities would be affected during the low water season.
These risk-augmenting mechanisms bearing on the biological cycles, could induce
sensitive, lasting transformations of rural production systems. Here are a few
possible trends:
The "high plains" are subject to a shallow submersion (less than 1.5 meters),
relatively short and random during bad years. These zones are predominantly dedicated
to rice culture and, later in the season, grazed on by the herds at the end of
the harvests.
The "low areas" benefit from a more systematic and deeper submersion, even in
years of bad floodings. These zones are predominantly dedicated to fishing and
husbandry and are used as shelter by animals throughout the dry periods (from
January to July).
One can predict that different zones will be differently concerned and affected
by the hydrological transformations caused by the Talo Dam.
The "high zones", whose submersion will become more random and with a lesser
intensity (height and duration), will become less attractive for the rice culture.
Furthermore, their exploitation to develop dry cultures (millet and sorghum)
won't be easy, since the land is not favorable to such cultures and submersion
would be damaging. Finally, the biomass of the pastures will decrease and so
will its workload, to also affect husbandry. These high plains will become less
and less productive, inducing an indifference to land ownership and cultivation.
The "low zones" will know other difficulties. The greater brutality from the
waters' arrival and the consequent increase of certain species' drowning invite
us to consider the hypothesis of a decrease in the biodiversity and the productivity
of the aquatic ecosystems. The drop of the average water level and the duration
of the inundation indicates a decrease of primary productions. Furthermore, these
already weakened zones will have to bear the influx of the rice-growers who will
unavoidably move toward these shallower zones to find conditions with sufficient
flooding (in height and duration) for rice growing. This move from farmers into
the low areas traditionally dedicated to husbandry will shrink the expanse of
pastoral spaces. It is feared that the tensions and conflicts between these two
types of users will yet likely increase.
Amongst the predictable adaptation forms, the mobility of the production
areas and of the local people themselves will no doubt be a major asset. But
land-owning law and capacity for mobility won't be identical for everyone. The
scope and frequency of the moves won't be the same according to the desired resources
and the concerned users. Mobility has been an essential foundation of the deltaic
production system for ever, yet it also poses a number of issues, that bring
its share of tensions and land-owning conflicts.
Recommendations
The failings we were able to identify in the preparation of the program ... are
all the more of concern, given that with such a Dam the upstream floodable zones
unavoidably threaten the abundance of resources, and therefore the social and
economical life of the valley. The preparation of this project must be reconsidered:
studies that demonstrate a real expertise are needed as well as a wider consultation
and an effective upgrade to current standards regarding Impact Studies. An objective
analysis, along with a critique of the project...will enable us to judge its actual
relevance and degree of priority in rural development policies. Two options then
become possible: give up the project or pursue it after having brought to it
significant improvements.
In the event of the project's continuation, it would be important to reconsider
all possible alternatives, such as: more complete technical solutions to allow
for a better management of water resources (rational utilization, allocation
amongst users); reduction of ecological impacts; and more economical profitability.
Particular care should also be given to the conditions related to popular participation
and to rural management of the settlements, which are issues often neglected.
Finally, land-owning issues, particularly sensitive in the Niger Delta in times
of decentralization, must be fully addressed.
Conclusion
The preparation of this Dam project suffers from enormous failings, -for instance,
the omission of the hydrological and economical impacts on the downstream area,
and of the ill-founded social and economical projections. However, we were able
to verify that this Dam will cause important hydrological and hydrographical
transformations ... These transformations will have unavoidable consequences on
space allocation and abundance of natural resources. Rural production systems
will be affected and local populations will have to resist -- rather than adapt
to -- new conditions in less generous environments. The indifference for certain
spaces (in high plains), for which submersion will become too random for rice-growing,
can be predicted. Alternately, deeper zones will be the object of fierce disputes,
with the need to renegotiate the traditional users' rights. The risks of land
disputes will no doubt increase.
Under these conditions, scientists and technicians must make it their duty to
work and supply accurate information, to shape opinions about the dangers that
threaten concerned societies, and point to available options. Presently, and
in order to do so, we cannot bypass the collecting of hydrographical and topographical
data that will allow more elaborate simulations and finer projections than the
ones we could produce in this work. One must also consider very closely the modalities
of consultation with the local populations, the modalities of the Dam's management
and of the settled land areas, and the expected impact on land-ownership.
5: Summary of Mr. François Gallier's DEA Geography DEA, held at Orléans IRD Center, September 12 2001. Contact: gallierfc@yahoo.fr
6: Initiated at the beginning of the 80s, the Talo Dam was part of a vast development scheme of the Bani, of which the main part was to be the Djenné Dam (Sedes 1984). Since then, the scheme has been abandoned, and inexplicably, the Talo Dam project has been pursued.
7: In hydrology, the decenial dry flood designates the weak flood, whose height will rise over nine years out of ten, statistically speaking.
8: in particular, the international association Cultural Survival has been engaged against the building of the Dam. The report from the Clark University is very critical of the project, and insists on its risks; it is available at: www.cs.org.
9: Refer to the documents from the Agrer office.
10: In light of the current contestation, the Banque Africaine de Developpement (BAD) has decided to postpone the financing of the project. Everything is on hold for now.
11: The cost of the construction is estimated at USD 27 million for the first phase.
12: Agrer, 1997, fig. 26, in particular.
13: Limnimetrical readings from national hydrological directorship.
14: This "Casier" is located at about 20 km south of Djenné, on the right bank of the Bani river. Work on a larger zone could definitely be considered in the zones mapped out by the Mopti Rice Office.
15: According to a response address to the Cultural Survival NGO 2001, Middle Bani Plains Improvement Program, and using data from SEDES 1984.
16: However, one must consider a number of factors related to the complex, unpredictable inter-relationships and we limit here the presentation of the dynamics and systems to the seemingly probable ones; any atttempt to quantify them would be, for now, illusory and questionable.
17: IIMI: National Institute for Irrigation Management.
* Translator's Note: rating curve: curve showing the relation between stage and discharge of a stream at a hydrometric station. If digitized, it is a rating table.
www.djenneintiative.org
Copyright 2004 © The Djenné Initiative, Inc.
|
|
|